File photo: Minister of Power, Joseph Tegbe The Federal Government has unveiled plans to increase Nigeria’s electricity transmission capacity by 984 megawatts through the upgrade of five transmission substations, as it intensifies efforts to address constraints preventing the evacuation of electricity to consumers. The projects, being implemented under the Presidential Power Initiative, will cover New Abeokuta, Onitsha, Ayede, Sokoto and Offa transmission substations, with the New Abeokuta project in Ogun State expected to account for 480MW of the additional capacity.
Context & Background
  • ✦The development comes as the government pushes to complete 16 transmission line projects covering 606.5 kilometres and advance the second batch of the initiative, which is expected to deliver another 3,376MW through additional substations and distribution infrastructure.
Key Figures & Named Entities
Friday:According to a statement issued by the Federal Government’s implementing agency, FGN Power Company, on Friday, the inspection assessed progress on the project, which involves transforming the existing 132/33kV facility into a modern 330/132/33kV transmission substation.2027:The statement read, “Ahead to 2027, FGN Power Company reaffirmed its commitment to accelerating the completion of all 16 Phase 1 transmission line projects spanning 606.5km, including the 38km Ajah–Shapaati line.” The upgrade, being undertaken by Siemens Energy, will involve the installation of two 300MVA transformers, alongside four 330kV and four 132kV transmission line bays.Today:He said, “Today’s inspection visit marks an important milestone in the delivery of the PPI and demonstrates the unwavering commitment of President Bola Ahmed Tinubu’s administration to transforming Nigeria’s power sector.
Outlook & Next Steps
Follow original publisher reporting for subsequent developments, official responses, and verified updates.
Key Takeaways
Verified Extract
  • ✦File photo: Minister of Power, Joseph Tegbe The Federal Government has unveiled plans to increase Nigeria’s electricity transmission capacity by 984 megawatts through the upgrade of five transmission substations, as it intensifies efforts to address constraints preventing the evacuation of electricity to consumers.
  • ✦The projects, being implemented under the Presidential Power Initiative, will cover New Abeokuta, Onitsha, Ayede, Sokoto and Offa transmission substations, with the New Abeokuta project in Ogun State expected to account for 480MW of the additional capacity.
  • ✦The development comes as the government pushes to complete 16 transmission line projects covering 606.5 kilometres and advance the second batch of the initiative, which is expected to deliver another 3,376MW through additional substations and distribution infrastructure.
Key Facts:Friday: According to a statement issued by the Federal Government’s implementing agency, FGN Power Company, on Friday, the inspection assessed progress on the project, which involves transforming the existing 132/33kV facility into a modern 330/132/33kV transmission substation.2027: The statement read, “Ahead to 2027, FGN Power Company reaffirmed its commitment to accelerating the completion of all 16 Phase 1 transmission line projects spanning 606.5km, including the 38km Ajah–Shapaati line.” The upgrade, being undertaken by Siemens Energy, will involve the installation of two 300MVA transformers, alongside four 330kV and four 132kV transmission line bays.Today: He said, “Today’s inspection visit marks an important milestone in the delivery of the PPI and demonstrates the unwavering commitment of President Bola Ahmed Tinubu’s administration to transforming Nigeria’s power sector.
Editorial Excerpt

The Federal Government plans a transmission substation upgrade at five sites to add 984MW to the grid, with New Abeokuta accounting for 480MW.

Frequently Asked Questions About This Story

What is the latest development regarding Bola Ahmed Tinubu?

File photo: Minister of Power, Joseph Tegbe The Federal Government has unveiled plans to increase Nigeria’s electricity transmission capacity by 984 megawatts through the upgrade of five transmission substations, as it intensifies efforts to address constraints preventing the evacuation of electricity to consumers.

Who are the key organizations or public figures mentioned?

The projects, being implemented under the Presidential Power Initiative, will cover New Abeokuta, Onitsha, Ayede, Sokoto and Offa transmission substations, with the New Abeokuta project in Ogun State expected to account for 480MW of the additional capacity.

What timeline or key figures were confirmed?

According to a statement issued by the Federal Government’s implementing agency, FGN Power Company, on Friday, the inspection assessed progress on the project, which involves transforming the existing 132/33kV facility into a modern 330/132/33kV transmission substation.